Received $20,000 Recreational Trails Program grant in 2005 from state of New Hampshire Trails Bureau. Used this to re-surface most of the 1.7 miles in Andover from Potter Place to Blackwater Park. Torrential rains forced postponement of part of this effort until May, 2006.
Received $30,000 Recreational Trails Program grant in 2006. It enabled
re-surfacing 2 miles from Blackwater Park to Switch Road in East Andover.
Received $30,000 Recreational Trails Program grant in 2007. Used this to
re-surface another 2 miles from Switch Road to Highland Lake in East Andover.
The 2008 Recreational Trails Program grant of $30,000 was used to improve the 2007 trail extension and to resurface nearly two miles of new trail between E. Andover and Dyer's Crossing.
Received $30,000 Recreational Trails Program grant in April, 2009. Used this to re-surface another 2 miles from Dyer's Crossing to Chance Pond Road in Franklin, NH.
|